ManagementSenior

Scrumban

Scrumban is a way of running a team that keeps Scrum’s regular meetings but swaps the sprint commitment for Kanban’s WIP limits and planning on demand. Corey Ladas coined the name in 2008 for a path from Scrum toward continuous delivery; most teams now use it for a stable hybrid. The page opens with every Scrum element and what becomes of it, then covers why the hybrid exists, the two meanings of the word, the three numbers that define it, how planned work and interrupts share one board, planning beyond the next fortnight, a side-by-side with its parents and one measured switch, and where it degrades.

Named by
Corey Ladas, 2008
Keeps from Scrum
Cadence, retrospective
Takes from Kanban
WIP limits, pull

Scrumban on one screen

Scrumban has no guide and no owning body, so the clearest definition is what it does to each part of Scrum. Here is every element of the Scrum Guide and what becomes of it — kept, changed or dropped — with the rule a team writes down in its place. Read it as the usual shape rather than a standard: teams vary, and the sections below say where.

Scrum elementIn ScrumbanThe rule written down instead
1. The SprintChanges: a fixed cadence for review and retrospective, no longer a batch of committed work"Every second Tuesday: review, then retrospective."
2. Sprint PlanningChanges: fires on a number, not on a date"When Ready holds fewer than 4 items, plan for 30 minutes."
3. Sprint GoalDropped as the commitment; some teams keep a goal per cadence as direction only"We commit to the WIP limits and the SLE."
4. Sprint BacklogReplaced by a capped, ordered Ready queue"Ready holds at most 8 items, in order."
5. Daily ScrumKept: walks the board right to left, blocked and oldest items first"15 minutes at the board; start with anything past the SLE."
6. Backlog refinementKept, and continuous — Ready must never run dry"Refine until Ready is full to its limit."
7. Sprint ReviewKept on the cadence, showing what shipped since the last one"Everything released since the last review, shown working."
8. Sprint RetrospectiveKept, non-negotiable — and now scheduled on purpose"A fixed slot in the calendar, whatever is in flight."
9. Product Owner, Scrum MasterOptional; most teams keep both"Who orders Ready, and who guards the policies."
10. Definition of DoneKept, plus exit criteria for every column"Done means released; Review exits on two approvals."
11. Velocity, story pointsDropped: cycle time and throughput instead"85% of items finish within 8 days."
12. IncrementReleased when done, or batched to the cadence"Release on done; demo on the cadence."

In one picture: a Kanban board with limits, a threshold under the Ready queue that calls planning when the queue runs low, and Scrum’s cadence running underneath on a fixed rhythm.

Work is pulled through Ready, Doing and Done under WIP limits. A threshold line under the Ready queue triggers planning when the queue runs low, replacing the fixed sprint start. The Scrum cadence of daily standup and retrospective continues underneath on a fixed rhythm.

Why it exists: the sprint that interrupts break

Here is the situation Scrumban solves. A team runs Scrum properly. Then production incidents start taking a third of its capacity, and it misses the three sprints in a row. Nobody did anything wrong — the goal was simply never realistic given the interruptions.

The arithmetic is short. A team that finishes about thirty items a fortnight plans a goal around thirty. If a third of every fortnight goes to incidents and requests that cannot wait, twenty are left for the goal — and the team does not know in advance which third of the fortnight it will lose. Planning twenty only works if the interrupts arrive at the same rate every sprint, and they rarely do.

What usually happens next is quiet decay. The team keeps holding sprint planning, keeps calling the fortnight a sprint, and everyone silently stops taking the goal seriously. The ceremonies remain and the meaning drains out of them. These are the signals that the shape of the work, not the team, is the problem:

SignalWhat it means
The Sprint Goal is missed three sprints running, for reasons outside the teamThe goal was never realistic under this interrupt load
Items are swapped into the sprint in the middle most weeksPriorities change faster than the sprint is long
Half the capacity is spoken for by support before planning startsInterrupts are a steady load and need their own lane and limit
The plan is out of date by the third dayThe batch is too large for how fast the team’s knowledge changes
Stakeholders ask about individual tickets, not about the goalThe goal no longer carries any information

Two meanings of the word

The word has drifted, and the drift explains most arguments about it. Corey Ladas, a former Microsoft development manager, coined it in a 2008 essay and expanded it into a 2009 book, "Scrumban: Essays on Kanban Systems for Lean Software Development". His Scrumban was a path, not a place: start from Scrum, change one practice at a time toward continuous flow, let the process stabilise, measure, and repeat.

In later remarks he put it bluntly. Scrumban, he wrote, is a deployment strategy for continuous delivery; it is not an approach to doing Kanban and not a set of practices. A team that reaches continuous delivery has, by his definition, left Scrumban behind.

Most teams that use the word today mean something else: a stable hybrid, reached by stopping partway along that path with the intention of staying. Two more texts have since drawn the line in other places. Ajay Reddy’s "The Scrumban [R]Evolution" (2015) treats Scrumban as the Kanban Method applied to a team that starts from Scrum. Scrum.org’s "Kanban Guide for Scrum Teams", written with Daniel Vacanti in February 2018 and revised in 2021, goes the other way: it adds WIP limits, flow measures and a to Scrum while keeping the and the Sprint Goal intact. That is Scrum with Kanban, and deliberately not Scrumban.

The word Scrumban draws its line in different places depending on who uses it. Corey Ladas, who coined it in 2008, meant a path: change one practice at a time from Scrum toward continuous flow, and leave Scrumban behind when you reach continuous delivery. Scrum.org’s Kanban Guide for Scrum Teams, 2018, stops early: it adds a visible workflow, WIP limits and flow measures but keeps the Sprint and the Sprint Goal, and calls the result Scrum with Kanban. Most teams that say Scrumban mean the middle: WIP limits, planning on demand and no sprint commitment, held as a stable hybrid. All three agree on WIP limits.
SourceWhat Scrumban isWhere it stops
Ladas, 2008–2009A path from Scrum toward continuous flow, one change at a timeIt ends: at continuous delivery the team is no longer doing Scrumban
Common usage since the 2010sA stable hybrid: Scrum’s cadence, Kanban’s limits and pullWherever the team stopped changing things
Reddy, 2015The Kanban Method applied to a Scrum contextAs far as the evidence takes it
Scrum.org, 2018Not Scrumban at all: Scrum with Kanban practices addedBefore the sprint changes: the Sprint and the Sprint Goal stay

The three numbers you must choose

Setting up Scrumban is mostly a matter of picking three numbers. Get these right and the rest follows; leave them vague and you have a board with no rules.

1. The WIP limit

Set it per column, not per person. A per-person limit lets everyone start something and still produces a board full of unfinished work.

A workable starting point is one and a half items per developer in the "in progress" column. For a team of four that is six. Then lower it over a few weeks until people occasionally hit it. The Kanban page has the arithmetic of why a lower number finishes work sooner.

2. The order point

This is the number that replaces the start of a sprint: when the Ready queue holds fewer than N items, planning is called. Ladas borrowed the idea, and its name, from inventory control, where a warehouse reorders stock when a shelf falls to a set level rather than on a set day. The level is chosen so that new stock arrives just before the shelf empties.

For a board the same arithmetic reads: order point equals items pulled per day, times the days it takes to hold planning and refine the new items, plus a small safety margin for a slow week.

Planning in Scrumban is called by a number rather than a date. The team finishes 1.6 items a working day, and calling a planning session and refining the new items takes a day and a half. With the order point at 4, the refill lands while 1.6 items are still waiting — that leftover is the safety margin, and the queue never runs dry. With the order point at 1, the same team runs out most of a day before its refill lands, and people have nothing ready to pull. The arithmetic is borrowed from inventory control: reorder when the shelf falls to what you will use while the new stock is on its way, plus a margin.

3. The retained cadence

Decide which Scrum meetings stay, and put them in the calendar as recurring events. The retrospective is mandatory. The daily meeting and a review every two weeks are usually worth keeping. Planning becomes on demand, called by the order point.

Planned work and interrupts on one board

The situation Scrumban is reached for usually has two kinds of work fighting over one team: work that can be planned and work that cannot wait. Kanban’s answer, and the one most Scrumban teams adopt, is capacity allocation. The WIP limit is split between kinds of work in advance, and each kind is drawn as its own horizontal lane with its own limit.

Capacity allocation splits a team’s work-in-progress limit between kinds of work in advance and draws each kind as its own lane. Expedite has a cap of one, which is the only defence against every request becoming urgent. Planned work is the one lane a stakeholder gets a forecast for, at that lane’s own throughput. Unplanned support has its own limit, so when it is full the next request waits instead of eating the planned work. Improvement always holds one item, never zero, because work with no deadline otherwise loses every argument to work with one.
LaneLimit, team of sixThe policy
Expedite1Jumps the queue and ignores the column limits. If a second one arrives, one of the two is not an emergency.
Planned5Pulled from Ready in order. The only lane a stakeholder is given a forecast for.
Unplanned3Support requests and small incidents, pulled as they arrive. When the lane is full, the next request waits.
Improvement1Technical debt and tooling, one at a time — always one, never zero.

The numbers are the policy, and they are argued once, calmly, at a retrospective, rather than for each request under pressure. If the unplanned lane is always full while the planned lane starves, the split was wrong: change it, and the change shows up in the measures rather than in anyone’s mood. The improvement lane’s limit of one is the most important number on the board. Without a guaranteed slot, work with no deadline loses to work with one every single time, and the system slowly decays.

Planning beyond the next fortnight

One question comes up as soon as the sprint goal disappears: how do you plan anything beyond the next two weeks? Ladas’s book answers it with bucket planning, or the three-bucket system. Work sits in one of three buckets, and items move forward one bucket at a time as they become clearer.

  • 1-year bucket

    Strategic direction. Vague statements of intent, no detail, no estimates. Reviewed a few times a year.

  • 6-month bucket

    Things the business has decided it wants. Shaped enough to discuss, not yet broken down.

  • 3-month bucket

    Ready to be refined and pulled onto the board. This is where the planning called by the order point draws from.

The point of the buckets is that detail is added only when an item moves forward. Nothing in the one-year bucket is estimated, because estimating something you may never build is the clearest form of wasted planning.

Two more mechanisms in the standard description of Scrumban are for the end of a fixed-date project, where a pull system meets a deadline — and they are the part most summaries leave out. A feature freeze means that as the date approaches, nothing new enters the board and only items already in progress continue. Triage follows straight after the freeze: someone with the authority to do it decides which items in progress will be finished and which will be stopped and taken off the board. Both are easy to describe and hard to do, and both exist because a pull system on its own does not know that a date is coming.

MechanismWhenWhat it prevents
Bucket planningContinuously; buckets reviewed on the slow cadenceEstimating work that may never be built
Order pointWhenever Ready falls to the thresholdA queue that runs dry, or one planned so far ahead it goes stale
Feature freezeA set time before a fixed dateNew work started that cannot finish in time
TriageStraight after the freezeEvery half-finished item arriving at the deadline together

Side by side with its parents, and one measured switch

AspectScrumScrumbanKanban
Planning triggerStart of sprintQueue below the order pointReplenishment cadence
CommitmentSprint GoalWIP limits and SLEWIP limits and SLE
Prescribed rolesThree accountabilitiesOptionalNone
RetrospectiveEvery sprintOn a fixed cadenceNot required; the cadences cover it
ForecastingVelocityCycle time and throughputCycle time and throughput
Mid-flight changeDiscouraged inside the sprintAllowed until an item is pulledAllowed until the commitment point
InterruptsAbsorbed by the sprint, or break itTheir own lane and limitA class of service or a lane

Siemens Health Services, 2012

The best-documented switch of this kind did not call itself Scrumban, but by this page’s definition that is what it was. Siemens Health Services had run Scrum since 2005. By 2012 its Soarian Financials programme — about fifteen Scrum teams in Malvern, Pennsylvania, in Brooklyn and in Kolkata — found that and velocity gave it no usable forecast at the scale of a release.

In May 2012 the teams dropped sprint planning, time-boxed sprints, story points and velocity, and moved to continuous pull with WIP limits, measuring cycle time and throughput on and scatterplots. They kept their engineering practices, their monthly retrospectives and their team and programme reviews. Bennet Vallet of Siemens reported the results in 2014:

MeasureResult
85th-percentile cycle time71 days before the switch; 43 in the first release on the new system, 41 in the second
Median cycle timeDown 21% from the first release to the second
ThroughputUp 33% from the first release to the second, with no change in story size or team make-up

Where it degrades

Scrumban is arrived at far more often than it is chosen. That is fine — but the arrival should be a decision, announced to stakeholders, rather than a drift nobody names. who were promised a sprint goal need to know that the commitment has changed shape. What they get instead is a forecast from measured cycle time, which is often more honest — but only if someone tells them the swap happened.

The honest limit: Scrumban fixes a mismatch between the shape of the work and the shape of the process. It does not reduce the interrupts; it only stops them breaking a promise they were always going to break. If a third of the team’s time goes to incidents, the useful question is why — and that question belongs to the retrospective and to whoever owns the system producing the incidents, not to the board.

  • Dropping the sprint commitment without adding a WIP limit — that is not Scrumban, that is an unbounded queue.
  • Keeping the sprint name and ceremonies while quietly ignoring the goal, which hides the change from stakeholders.
  • No order point, so planning happens when someone remembers and the queue runs dry.
  • The retrospective lapsing because no sprint boundary forces it into the calendar.
  • still reported upward alongside cycle time, so the team is judged on a number its process no longer produces.
  • An lane with no limit, which turns the whole board back into an interrupt queue.
  • No improvement lane, so technical debt waits for a sprint that no longer exists.
  • Sprints announced on the calendar while items are swapped on the board every day — Scrum in name, no process in fact.
  • Adopted to escape the discipline of Scrum rather than to fit the shape of the work.

When to use it

Use it when

  • The team mixes planned work with a steady stream of interrupts — platform, maintenance, internal tooling.
  • A Scrum team keeps missing its Sprint Goal for reasons outside its control.
  • You want Kanban’s flow but would lose the retrospective if you dropped Scrum entirely.
  • Work items are small and similar enough that a goal adds less value than throughput does.

Avoid it when

  • The team needs a shared goal to coordinate around — keep Scrum, and add flow measures to it instead.
  • It is being adopted to escape discipline rather than to fit the work.
  • The organisation plans by sprint, so a team without sprints becomes invisible to it.
  • You have not yet run Scrum or Kanban properly — learn one before blending them.

Sources and method

What this page stands on

  • 8 sources
  • Checked October 13, 2026

Practices and where the terms come from

where the word comes from, its two meanings and the three numbers

Researched with Claude. Finding and cross-checking the primary sources was done with Claude (Anthropic). Selection, writing and fact-checking: the Anatomy of IT Product editors.

Found this useful?

Share it with someone who is working on the same problem.